Question: 1
Where can you enter a rounding profile?
Note: There are 2 correct answers to this question.
A. Lot-sizing procedure
B. Purchasing info record
C. Source list
D. Material master
Answer: B D
Question: 2
What is the definition of an opening horizon?
A. The time available for the MRP run to convert a requirement into a schedule line or a planned order
B. The time available for the MRP run to convert requirements into purchase requisitions or planned orders
C. The time available for the MRP controller to convert a purchase requisition into a purchase order or a schedule line
D. The time available for the MRP controller to convert a planned order into a purchase requisition or a production order
Answer: D
Question: 3
Which of the following procurement proposals can be created during an MRP Live planning run for externally procured materials? Note: There are 2 correct answers to this question.
A. Planned order
B. Purchase order
C. Delivery schedule line
D. Purchase requisition
Answer: C D
Question: 4
Which of the following tasks does the system perform during reorder point planning? Note: There are 2 correct answers to this question.
A. Flag materials that have been subject to an activity relevant to MRP
B. Carry out a lot-size calculation for every material with net requirements
C. Carry out a net requirement calculation for every material included in the planning run
D. Perform backward scheduling to determine the availability dates of purchase requisitions
Answer: B C
Question: 5
What does SAP S/4HANA use to determine the sequence in which materials are planned?
A. Source list
B. MRP group
C. Low-level code
D. Quota arrangement
Answer: C