-92%New
Question: 1
During an inspection the lab technicians record the same test values for an inspection characteristic.
Which of the following do they assign to the products?
A. As a sample size
B. As an inspection point
C. As a partial lot
D. As a batch
Answer: B
Question: 2
What is required in inspection planning to transfer a characteristic value from results recording of inspection lot processing………
A. Configuration settings
B. Settings for the inspection type activated in the material level
C. Master inspection characteristic linked to class characteristics
D. Usage of the class characteristics in the task list
Answer: C
Question: 3
When creating a process order, what type of task list is primary used for inspection ? Correct 3
A. Routings
B. master recipe
C. Equipment
D. Reference rate routing
Answer: A, B, D
Question: 4
You have determined a new business inspection process and need to customize a new inspection type
Which of the following activities must you complete? Correct 2
A. Define goods movement type
B. Assign inspection type to inspection lot origin
C. Define default values for inspection type
D. Assign Task list type to material types
Answer: B, C
Question: 5
In the material master, at which organizational level do you create Quality management (QM) data for inspection type.
A. Client level
B. Plant level
C. Business area level
D. Company code level
Answer: B