Question: 1
What are valid procurement types for stock items? Note: There are 3 correct answers to this question
A. Preliminary purchase requisition for WBS element
B. Planned order
C. Third-party order
D. Purchase requisition and Reservation for WBS element
E. Reservation for WBS element
Answer: A, D, E
Question: 2
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct answers to this question
A. Material master
B. Network activity
C. WBS element
D. BOM item
Answer: B, D
Question: 3
When you create a service activity in your network, what data can be entered? Note: There are 3 correct answers to this question.
A. Service specification
B. Overall limit (maximum value of all unplanned services)
C. Service purchase order number
D. Material master within service specification
E. Vendor
Answer: A, B, E
Question: 4
Float time is calculated during scheduling.
Which of the following statements about float time are correct? Note: There are 3 correct answers to this question
A. Float time can be negative
B. Activities with the time constraint “Must start on” always have a negative float time
C. The float time of WBS elements is calculated by extrapolation
D. By default, critical activities have a float time, which is less than or equal to zero
E. The maximum size of a free float is as large as the total float of an activity
Answer: A, B, E
Question: 5
You have created an internally-processed network activity, and assigned a work center and the work. After saving, you discover that no planned costs are displayed in the cost element report for the activity. What could be the reason? Note: There are 3 correct answers to this question
A. The formula for costing in the work center is incorrect
B. The activity output price for the activity type and cost center assigned to the work center is not maintained.
C. The duration is missing in the activity
D. The Determine Costs indicator in the network header rules out planned cost calculation
E. Integrated planning for the network is active
Answer: A, B, D